Bathroom Renovation Checklist: What to Buy and When

Renovated bathroom with a wall-hung timber vanity, brushed nickel wall mixer, frameless shower and linear floor waste

Quick answer: anything that goes inside the wall or floor has to be bought and on site before the plumber's rough-in. That means in-wall cisterns, wall mixer bodies, shower wastes and floor-mounted bath fillers. Big items like the vanity, bath and toilet should be ordered early, because they go by freight and can take time. The visible finishing pieces, like mixer trims, the toilet pan, mirror and accessories, aren't needed until fit-off, after tiling.

Get the order wrong and the tiler either waits on site or has to come back, and neither is cheap. This checklist walks through each stage.

The renovation at a glance

Stage Who's on site What you need ready
1. Plan and measure You, designer or builder Layout, finish, product list, permits
2. Demolition Builder Long-lead items ordered
3. Rough-in Plumber, electrician In-wall cistern, mixer bodies, wastes, bath filler rough-in
4. Waterproofing and tiling Waterproofer, tiler Shower base or channel waste, tile inserts, tiles
5. Fit-off Plumber, electrician, carpenter Vanity, basin, toilet pan, mixer trims, mirror, accessories
Timeline of a bathroom renovation showing what to buy at each stage: plan, order, rough-in, waterproof and tile, fit-off

Stage 1: Plan and measure (4 to 8 weeks out)

Most problems start here, so take your time.

  • Lock in the layout. Decide where the vanity, shower, bath and toilet go. Keeping them where the plumbing already is will save you real money.
  • Measure everything twice. Wall widths, door swing, ceiling height, and the toilet set-out (the distance from the wall to the centre of the waste pipe).
  • Pick one finish and carry it through tapware, accessories and the door hardware. Our finish guide compares how each one holds up.
  • Check approvals. Apartments usually need strata approval. Structural changes may need council approval.
  • Write the product list and mark each item as rough-in or fit-off. That list is what your plumber and tiler will work from.

Stage 2: Order the long-lead items

Boxed bathroom vanity, bath and toilet stored in a garage before installation

Vanities, baths, toilets and shaving cabinets are big, heavy and usually go by freight. Order them as soon as the layout is final, even if they won't be installed for weeks. It's better to store a boxed vanity in the garage than to hold up the job waiting for one.

Check everything when it arrives, before the trades need it. Faulty or damaged items are covered under Australian Consumer Law, but it's much easier to sort out early than on the day the plumber's booked.

Stage 3: Before rough-in, these must be on site

Bathroom at rough-in stage with an in-wall toilet cistern frame and shower mixer body fixed between timber studs

This is the stage people get caught out on. Once the walls are sheeted and waterproofed, it's too late to change anything inside them.

  • In-wall cistern and frame for a wall-hung toilet, like the Geberit Sigma 8 Duofix. It's built into the wall framing.
  • Wall mixer bodies for the shower, bath and any wall-mounted basin mixer. Systems like Phoenix SwitchMix use a body that sits inside the wall, with the visible trim fitted later.
  • Wall spouts and shower arms, so the plumber knows the exact outlet positions and heights.
  • Shower and floor wastes, including linear channel wastes like the Meir 900mm channel with tile insert.
  • Floor-mounted bath filler, like the Meir Harrington. Its pipes come up through the floor, so the position must be set now.
  • Anything electrical: heated towel rails, LED mirrors and shaving cabinets with power, like the Otti LED Bondi, need their wiring run by a licensed electrician at this stage.

All plumbing has to be done by a licensed plumber, and in Victoria a compliance certificate is required for plumbing work over $750. Ask your plumber for it.

Stage 4: Waterproofing and tiling

Tiled shower floor with a stainless steel linear channel waste and tile insert sitting flush

Waterproofing in wet areas has to meet the Australian Standard AS 3740, and it's one of the most common sources of building defects, so use a qualified waterproofer and don't let anyone rush it. Take photos of the waterproofing before the tiles go on.

Have the tiler confirm the shower waste and tile insert sizes before they start, and make sure the falls run towards the waste. If you're tiling up to a freestanding bath or a wall-hung vanity, give the tiler the exact dimensions now.

Stage 5: Fit-off

Plumber fitting the trim and lever of a brushed nickel wall mixer onto a tiled shower wall

After tiling, the plumber and electrician come back to fit everything you can see:

These are the pieces you see every day, so it's worth checking that every finish matches before the plumber leaves. Sticking to one range makes that easy: Phoenix Vivid Slimline, for example, covers the wall mixer, fit-off kit, shower and towel rails in the same design.

Common mistakes

  • Buying the pretty bits first and the in-wall parts last. It should be the other way round.
  • Not measuring the toilet set-out before choosing a toilet.
  • Choosing a freestanding bath filler after the floor is done. Its plumbing has to go in at rough-in.
  • Forgetting power for a heated towel rail or LED mirror until the walls are tiled.
  • Mixing brands of tapware and accessories in the same finish, then finding the shades don't quite match.
  • Ordering the vanity too late and holding up the plumber's fit-off.

Your bathroom checklist

Before rough-in

  • ☐ Layout, measurements and toilet set-out confirmed
  • ☐ Finish chosen
  • ☐ In-wall cistern and frame (if wall-hung)
  • ☐ Wall mixer bodies for shower, bath and basin
  • ☐ Shower waste or channel waste
  • ☐ Floor-mounted bath filler (if freestanding bath)
  • ☐ Wiring plan for heated towel rail, LED mirror or shaving cabinet
  • ☐ Vanity, bath and toilet ordered

Before fit-off

  • ☐ Mixer trims and spouts
  • ☐ Toilet pan, seat and flush plate
  • ☐ Basin, pop-up waste and basin mixer
  • ☐ Shower rail or head, and shower screen
  • ☐ Mirror or shaving cabinet
  • ☐ Towel rails, hooks and toilet roll holder
  • ☐ Privacy handle for the bathroom door

Products mentioned in this guide

Buy before rough-in

Buy before fit-off

Getting it all from one place

Buying everything from one supplier makes it easier to match finishes and keep deliveries on schedule. Browse our bathware, showers, vanities and toilets.

Vanities, baths and toilets go by freight and aren't included in free shipping, but you can collect them from our showroom at 169 Para Road, Greensborough. Everything else ships free over $500, and most orders arrive in 2 to 5 business days. If you'd like help putting together a product list for your plumber, call us on 03 9017 0217. The advice is free, and builders can ask about a trade account.

Frequently asked questions

What do I need to buy before the plumber does the rough-in?

Anything that goes inside the wall or floor: in-wall cisterns, wall mixer bodies, shower and floor wastes, and floor-mounted bath fillers. Your plumber needs these on site to set the pipe positions.

What is the difference between rough-in and fit-off?

Rough-in is when the plumber and electrician run pipes and wiring inside the walls and floor, before waterproofing and tiling. Fit-off is when they come back after tiling to install everything you can see, like tapware, the toilet and the vanity.

How far ahead should I order a vanity?

As soon as your layout is final. Vanities go by freight and can take a while, so it's better to have one stored in the garage than to hold up the plumber's fit-off waiting for it.

When do I need to choose a freestanding bath filler?

Before rough-in. A floor-mounted filler has its pipes run up through the floor, so its exact position has to be set before the floor is waterproofed and tiled.

Do I need a licensed plumber for a bathroom renovation?

Yes. In Australia, any work connected to water supply or drainage must be done by a licensed plumber. In Victoria, a compliance certificate is required for plumbing work over $750.

What waterproofing standard applies to bathrooms in Australia?

Wet area waterproofing must meet Australian Standard AS 3740. Use a qualified waterproofer and photograph the waterproofing before it's tiled over.